Wawona Road Rehabilitation work 6/22 &23

 

Wawona Road Rehabilitation (June 1 - November 2010):

6/22/10
  *Today's locations of work: Today, contractors will be installing curb
  in the 5 mile section that begins 1 mile north of the Wawona Campground
  and runs north.  They will also be surveying in the 2 mile section south
  of the Wawona Tunnel and installing string line for curbing in the 6
  mile section south of the Glacier Point Road intersection (Chinquapin).
  *Tonight's locations of work: Tonight, they will installing culverts,
  installing underdrain crossings, and grinding pavement for a water line
  in the 6 mile sections south of and north of the Glacier Point Road
  intersection (Chinquapin).
  *Wednesday's locations of work (June 23)  On Wednesday, they will be
  installing curb in the 5 mile section that begins 1 mile north of the
  Wawona Campground and runs north.

For daily traffic control updates, call the park information line at (209)
372-0200 (then press 1, and 1 again).