31
| 1
Start: 06/01/2010
Glacier Point Road Rehabilitation (June 1 - 11, 2010)
Crews will be working at multiple locations along the Glacier Point Road as
well as on the Wawona Road at the Chinquapin Intersection with the
following delays Monday morning 6:00 am through Friday night at 4:30 pm.
Weather permitting, construction is anticipated to be completed by June
11th.
6:00 AM to 7:30 AM 15-Minute Delays
7:30 AM to 3:30 AM 30-Minute Delays
3:30 PM to 4:30 PM 15-Minute Delays
4:30 PM to 11:00 PM 30-Minute Delays
Start: 06/01/2010
It Appears that this project is finished. 6/23/10
Tioga Road Pavement Borings(June 7 - July 1, 2010) Beginning June 7 crews will be completing pavement borings on the Tioga Road between Crane Flat and Tuolumne Campground with up to 15-minute traffic delays, Monday through Friday with no weekend delays. This work is being conducted in preparation for a future rehabilitation project.
| 2
all day
Glacier Point Road Rehabilitation (June 1 - 11, 2010)
Crews will be working at multiple locations along the Glacier Point Road as
well as on the Wawona Road at the Chinquapin Intersection with the
following delays Monday morning 6:00 am through Friday night at 4:30 pm.
Weather permitting, construction is anticipated to be completed by June
11th.
6:00 AM to 7:30 AM 15-Minute Delays
7:30 AM to 3:30 AM 30-Minute Delays
3:30 PM to 4:30 PM 15-Minute Delays
4:30 PM to 11:00 PM 30-Minute Delays
all day
It Appears that this project is finished. 6/23/10
Tioga Road Pavement Borings(June 7 - July 1, 2010) Beginning June 7 crews will be completing pavement borings on the Tioga Road between Crane Flat and Tuolumne Campground with up to 15-minute traffic delays, Monday through Friday with no weekend delays. This work is being conducted in preparation for a future rehabilitation project.
| 3
all day
Glacier Point Road Rehabilitation (June 1 - 11, 2010)
Crews will be working at multiple locations along the Glacier Point Road as
well as on the Wawona Road at the Chinquapin Intersection with the
following delays Monday morning 6:00 am through Friday night at 4:30 pm.
Weather permitting, construction is anticipated to be completed by June
11th.
6:00 AM to 7:30 AM 15-Minute Delays
7:30 AM to 3:30 AM 30-Minute Delays
3:30 PM to 4:30 PM 15-Minute Delays
4:30 PM to 11:00 PM 30-Minute Delays
all day
It Appears that this project is finished. 6/23/10
Tioga Road Pavement Borings(June 7 - July 1, 2010) Beginning June 7 crews will be completing pavement borings on the Tioga Road between Crane Flat and Tuolumne Campground with up to 15-minute traffic delays, Monday through Friday with no weekend delays. This work is being conducted in preparation for a future rehabilitation project.
| 4
all day
Glacier Point Road Rehabilitation (June 1 - 11, 2010)
Crews will be working at multiple locations along the Glacier Point Road as
well as on the Wawona Road at the Chinquapin Intersection with the
following delays Monday morning 6:00 am through Friday night at 4:30 pm.
Weather permitting, construction is anticipated to be completed by June
11th.
6:00 AM to 7:30 AM 15-Minute Delays
7:30 AM to 3:30 AM 30-Minute Delays
3:30 PM to 4:30 PM 15-Minute Delays
4:30 PM to 11:00 PM 30-Minute Delays
all day
It Appears that this project is finished. 6/23/10
Tioga Road Pavement Borings(June 7 - July 1, 2010) Beginning June 7 crews will be completing pavement borings on the Tioga Road between Crane Flat and Tuolumne Campground with up to 15-minute traffic delays, Monday through Friday with no weekend delays. This work is being conducted in preparation for a future rehabilitation project.
| 5
all day
Glacier Point Road Rehabilitation (June 1 - 11, 2010)
Crews will be working at multiple locations along the Glacier Point Road as
well as on the Wawona Road at the Chinquapin Intersection with the
following delays Monday morning 6:00 am through Friday night at 4:30 pm.
Weather permitting, construction is anticipated to be completed by June
11th.
6:00 AM to 7:30 AM 15-Minute Delays
7:30 AM to 3:30 AM 30-Minute Delays
3:30 PM to 4:30 PM 15-Minute Delays
4:30 PM to 11:00 PM 30-Minute Delays
all day
It Appears that this project is finished. 6/23/10
Tioga Road Pavement Borings(June 7 - July 1, 2010) Beginning June 7 crews will be completing pavement borings on the Tioga Road between Crane Flat and Tuolumne Campground with up to 15-minute traffic delays, Monday through Friday with no weekend delays. This work is being conducted in preparation for a future rehabilitation project.
| 6
all day
Glacier Point Road Rehabilitation (June 1 - 11, 2010)
Crews will be working at multiple locations along the Glacier Point Road as
well as on the Wawona Road at the Chinquapin Intersection with the
following delays Monday morning 6:00 am through Friday night at 4:30 pm.
Weather permitting, construction is anticipated to be completed by June
11th.
6:00 AM to 7:30 AM 15-Minute Delays
7:30 AM to 3:30 AM 30-Minute Delays
3:30 PM to 4:30 PM 15-Minute Delays
4:30 PM to 11:00 PM 30-Minute Delays
all day
It Appears that this project is finished. 6/23/10
Tioga Road Pavement Borings(June 7 - July 1, 2010) Beginning June 7 crews will be completing pavement borings on the Tioga Road between Crane Flat and Tuolumne Campground with up to 15-minute traffic delays, Monday through Friday with no weekend delays. This work is being conducted in preparation for a future rehabilitation project.
|